You must to know
First time PLC S7-1200Very important is understand the objetive of the Project
If you want to understand this project so easy you could have learnt Configuring for first time PLC S7-1200 Siemens and Also Configuring and Programming Analog Inputs 4-20mA in S7-1200 Siemens
PROJECT OBJECTIVE
The Project start as "Experiment" and we want to Dry the Waste that comes from a Wastewater Treatment Plant.....but what means it?
All the waste from Wastewater Treatment Plant must to be in Temperature for his dried and after "Reuse" for other purpose; it means this project search Dry into a "Greenhouse" that inside the Temperature is higher than Outside, is if higher you think it dries faster? but remember you have some other points to consider:
ENGINEERING INFORMATION
All the projects always may be of better features, in this case is a "Pilot Experiment Project" it means is a experiment that works a team of Engineers, Safety, Chemicals, etc; it means the Project of Instrumentation must to be Friendly and easy to operation with all Professionals, the configuration that we design is very important for the project
Important Engineering Documentation
CHOISING DEVICES
As in all Control Projects, Choose the best PLC is always a challenge because you must to consider the Price, Difficult, Reliability, etc, Remember Learn to Choose a PLC for this project we choose PLC S7-1200 Siemens; WHY? Robust, Reliable, Normal Software and Enough for this project
The final Electromechanical Signals are:
A Project Electromechanical always include Power and Control
Always must to be clear in know all the Electrical Control elements as:
First we draw the first Layout of POWER recognizing all motors and loads, powering by electric supply, very important
Download Electrical Power Layout (PDF)Next begin to design the Electrical Control System
Download Electrical Control Layout (PDF)In All Electrical Projects is very important draw the distribution of Power Loads
Download Distribution Power Layout (PDF)Instrumentation, Engineering and Control most important Points in Project
DEVICES AND PARAMETERS
First we identify most important variables and parameters to measure in the process:
Now is very important always have in consideration before choose an Instrument technical features of the enviroment:
CHOOSE PLC
The final information we have obtained let's define:
BUT we can see our PLC have all Digital Outputs used, So we add a Module Relay Outputs to the PLC... remember to see in details Learn to Choose a PLC Here, the PLC we have choosed and the Modules may looks like this:
The final Hardware choosed for this project is:
CONTROL CONNECTIONS
One of the most complex points is understand 100% the connections of all the Process; so we have to define:
Wire and Connections of Transmitters / Sensors by Manufacturer
Typical Sensors Wire Diagram 2-3-4 Wires in Analog Input Module AI S7-1200
This is the important moment to Programming and Configure in Software
Remember you can learn from 0 Learn for first time PLC S7-1200 and if you want to be smarter Scale and Activate Analog Inputs in 4-20mA in PLC S7 1200
Them choose the Right CPU 1214 in this case and begin to configure:
Add the IP to our CPU
Add the Expansion Modules Analog AI SM1231 and Output Relay SM1222 to our CPU
In this case gonna work with Transmitters 4-20mA; So we gonna configure All Analog Inputs of the Analog Modules in Current 4-20mA
Other point VERY IMPORTANT; Configure with order the Sensors in both Modules Added; in this moment and with all information watched, we must to be clear in what we are doing
Digital Inputs and Outputs in CPU and Module DO Relay looks like this:
SCALE SENSORS
Other very important point is Scale Correctly the Sensors/Transmitters, this point is very important if we want that the project will be an success!
The Draeger Transmitters must to be configured for Specialists (in Transmitters), Reason? They make real test with Gas NH3; H2S & Covs; Control Engineer Scale and Configure in PLC and by other side Draeger Specialist configure and test from Transmitter
First start to Normalize NORM and then to SCALE for more details Scale Analog Inputs 4-20mA in PLC S7 1200
Now that we have the information in orden begin to create the variables SCALE and NORM for each of our 14 Sensors/Transmitters
Finally Normalize and Scale all Sensor 1 for 1; remember the Range Measurement:
Until the moment we have worked and Scaled the 14 Analog Sensors, it's time to Monitoring in SCADA by a Weintek HMI Touchscreen MT8070iE
Create a Design SCADA and Monitoring by Weintek the PLC S7-1200
EXPORT Tags: from TIA PORTAL
Now go to Easybuilder Pro Software, if you don't have installed this Software is FREE How Download and install Software HMI Weintek Easybuilder Pro
Select the PLC S7-1200 Siemens and assign SAME IP 192.168.0.2 that we configure our CPU from TIA Portal (Step 4)
This is the moment for IMPORT TAGS that we before Export from TIA PORTAL
MONITORING SENSORS
Insert the blocks NUMERIC; here is the Configuration to Monitoring AI, IMPORTANT You must to select the FINAL SCALED VALUE For each one of the 14 Sensors
Configure the information, the importan is "Decimals or Integers"; for NH3 is 0-300 and must to consider 3 Digits; and for other 2 Sensors 0-50 we configure 2 Digits
Example of Configuration of Sensor H2S with TAG ADDRESS and Format
Finally to design our SCADA Add our 14 Sensors and we can write in Screen for recognize it
COMPILE and SIMULATE OFF LINE, we can see our 14 Sensors in HMI, remember the value showed is the "Final Scaled Value" from PLC S7-1200
The Download are FREE and you can get Connections and Documents (PDF)
ELECTRICAL LAYOUT POWER & CONTROL
DOCUMENTS & USER MANUAL